NCDP Library Construction Progress Update – December 24, 2025
Dear KCFC (Kazoza Care For Children for Education),
Cc: Prof. Aggrey Wasike
We are excited to share the latest update on the ongoing construction of the NCDP Library in Bihororo Village.
As of December 24, 2025, we are proud to report that the project has reached 95% completion. The electricians have successfully installed all lighting fixtures and 16 security cameras to ensure safety and monitoring throughout the facility.
The final phase of the project includes the installation of:
• Desks and chairs
• Computers
• A collection of books and other learning materials
We remain committed to our mission of promoting rural and human development through education and thank you for your continued support.
Best regards,
Alphonse Nahimana
CEO & Founder, Nuragira Community Development Project (NCDP)




Related Posts
Fresh water factory, named ‘Nyakigoti,’ is under construction in Bihororo village.
“The NCDP Water Solution fresh water factory, named ‘Nyakigoti,’ is under constr...
The employees of NCDP-Munyamwete Construction Company celebrated Easter at their headquarters in Bihororo, Mugondo.
This week, the whole world is in celebration and remembrance of our Lord Jesus C...
CDP Construction Update: April 2, 2026, Bakery Facility Infrastructure:
Location: NCDP Site, Ku Mugondo, Bihoro Village, Masango NCDP Construction Updat...