CDP Construction Update: April 2, 2026, Bakery Facility Infrastructure:

Location: NCDP Site, Ku Mugondo, Bihoro Village, Masango

NCDP Construction Update: April 2, 2026

Location: NCDP Site, Ku Mugondo, Bihoro Village, Masango

As of April 2, 2026, notable advancements have been achieved at the NCDP construction site, overseen by NCDP-Muryamwete Construction Company. The team is working diligently to adhere to the project deadline scheduled for August 2026.

Current Status of Construction:*

1.⁠ ⁠Bakery Facility Infrastructure: The bakery facility is nearing completion, with approximately 90% of construction finalized. This facility is anticipated to be instrumental in enhancing local food production and improving community nutrition.

2.⁠ ⁠Upcoming Infrastructure: The foundation for the next phase of construction has been successfully completed. This new structure will encompass various essential services, arranged across upper and lower levels:

  • Upper Level Services:
    • NCDP-TV Masango Head Office: This will function as the central hub for broadcasting and media operations.
    • Two Offices for NCDP Human Resources: These offices will support the administrative needs of the project.